CNC machining tolerances: ISO 2768, drawings and CMM.
Tolerance questions decide both the manufacturing route and the quotation. This guide explains how general tolerance standards, drawing-specified values and CMM verification fit together.
Where a tolerance requirement actually comes from
The drawing is the controlling document. ISO 2768 covers un-toleranced dimensions only — it does not apply to individually toleranced features. Mating, sealing and parallelism requirements belong on the drawing explicitly, with datums. A "ISO 2768-mK" note is a starting point, not a complete precision specification.
How tolerances are read during review
Review order: datum system → individually toleranced features → general-tolerance note. The checks: are datums connected, is the inspection condition stated, do coating or heat treatment change what a value means. Ambiguities become questions before quoting, not findings after inspection.
What the inspection equipment covers
A dedicated Mitutoyo LEGEX 774 CMM with a 700 × 700 × 450 mm measuring range. Measuring range is not maximum part size — geometry and fixturing bound that. Inspection scope, frequency and report format are part of the quotation.
What project records show (project-specific values)
- Thin-wall enclosure cover: flatness ≤ 0.05 mm — 6061-T651, 426 × 221 × 36 mm
- Rotary engine housing: bore coating 0.15 ± 0.01 mm, Ra ≤ 0.12 µm after HVOF and profile grinding
- Brass RF housing: CMM inspection of channels, mating faces and locating features
How tolerance decisions affect the quotation
Tight tolerances add steps: post-coating or post-heat-treatment inspection, fixturing and stress relief on thin sections, and real CMM report time. Mark only the truly critical features — cost should follow risk.
What to specify in your RFQ
| Decision | Why it matters |
|---|---|
| Tolerance critical features individually | General standards cover un-toleranced dimensions only |
| State datums and inspection condition | Flatness and parallelism need datums and a stated condition |
| Confirm verification stage post-coating / HT | Values may apply to the finished surface, not the machined one |
| Name the report format | CMM, roughness and coating reports are agreed per project |
Representative critical tolerances in published cases: ±0.01 to ±0.02 mm — assessed per drawing, not assumed.